Description:
SAO Energy successfully installed a 10kW solar power system at the Ondo State Primary Healthcare Development Agency (OSPHCDA) office complex. The installation includes two 5kVA hybrid inverters, fifteen 450W solar panels, and three 5kWh batteries.
The system generates 13.5kWp of solar energy daily, paired with a 15kWh battery storage system, ensuring 24/7 power supply. This installation replaced a 20kVA Lister generator, reducing annual CO2 emissions by 29,346 kg. The project significantly cut operational costs, as the offices were powered by diesel generators.
Products Used for this Project:
- Solar Panels: 15 units of 450W monocrystalline panels
- Inverters: 2 units of 5kVA hybrid inverters
- Batteries: 3 units of 5kWh batteries